Pars Industrial Soot Factory
CLIENT: Pars Industrial Soot Factory










Engineering, procurement and construction (EPC) services for the Potash Processing and Production Plant and its by-products from the brines of the Central Iranian Desert (Khor and Biabanak) were carried out between 1999 and 2007. The scope of work included technical consulting and supervision, engineering and technology services, procurement and logistics, construction, installation, commissioning of industrial facilities and supporting buildings. The project was executed under the patronage of the Ministry of Mines and Metals – General Iranian Mines Joint Stock Company and consisted of several major sub-projects.
Engineering studies and selection of suitable equipment and operational methods for extracting salt and carnallite from the project evaporation ponds.
Procurement and supply of pilot plant equipment required for semi-industrial production and process validation.
Excavation and construction of approximately 3.5 kilometers of brine collection channels to support raw material transfer operations.
Procurement of GRP pipes and fittings for the brine transmission line connecting Playa to the solar evaporation ponds.
Engineering, purchasing and supply of industrial valves required for the brine transfer pipeline system.
Procurement and supply of crushing equipment and related machinery required for mineral processing operations.
Purchase and supply of electropumps designed for efficient brine transportation throughout the processing system.
Engineering procurement of polyethylene pipes and associated fittings for supporting utility and transfer networks.
Construction of sections S5 and S6 of the solar evaporation ponds to support mineral concentration and production processes.
Construction of pumping stations, supporting structures, freshwater resources and compressed air facilities required for plant operation.
Purchase, installation and commissioning of mechanical and electrical equipment for the brine pumping stations.
Preparation of technical agreements, general and specific conditions for the procurement, transportation, installation and commissioning of the power plant overhead crane.
Construction and implementation of the complete brine collection and transfer line from Playa to the pumping station.

CLIENT: Pars Industrial Soot Factory

CLIENT: Mianeh Steel Complex

CLIENT: Ministry of Mines and Metals – General Iranian Mines Joint Stock Company